Recently, in a case involving a construction group company represented by King&Capital Law Firm against a civil aviation airport company regarding a dispute over a construction contract, the firm secured a complete victory after the case went through the first-instance proceedings at the Intermediate People’s Court, the second-instance proceedings at the Higher People’s Court, and the retrial review process at the Supreme People’s Court. The project in question was a civil aviation airport construction project in a certain city. As the contracting party, the civil aviation airport company had completed the audit of the final settlement and signed a settlement agreement with the general contractor regarding the full project payment. The client, as the actual contractor, believed that the settlement audit contained errors and that the settlement agreement between the contracting party and the general contractor could not be enforced against the actual contractor; therefore, the client claimed the difference in the project payment settlement from the civil aviation airport company. The client had previously filed three lawsuits in local courts, but due to various pressures and factors, none of these cases made substantial progress. After accepting the case, the King&Capital Law Firm team successfully applied for an upgrade in jurisdiction and initiated a new judicial appraisal of the project in question, thereby overturning the original audit conclusions and securing tens of millions of yuan in project payments for the client.
1
Airport Completed and Opened for Operations; Actual Contractor Faces Incorrect Settlement
During the construction of the airport project in question, because on-site conditions did not conform to the original design, the design firm issued a change notice, resulting in modifications to the construction methods for the airport runways, which significantly increased construction costs. Upon completion of construction and following the final acceptance inspection, the airport was officially opened for operations. However, the Civil Aviation Airport Company and the general contractor finalized the settlement review without notifying the client or seeking their input. They approved a settlement amount of over 200 million yuan, which was paid in full, and subsequently signed a settlement agreement. Subsequently, the client discovered that the final settlement either failed to account for the additional work volume resulting from the aforementioned major design changes or settled it at an unreasonably low rate. Thus, the client’s actual construction investment—amounting to tens of millions of yuan—was effectively “wiped out” by a single settlement document.
2
Three Lawsuits and a Successful Application for Elevated Jurisdiction
The client filed lawsuits in 2021 and 2023 with the courts in the jurisdiction where the project was located. However, due to the case involving multiple complex legal issues—such as the identification of the actual contractor, the validity of settlements between the project owner and the contractor, and the admissibility of construction cost appraisals—as well as the large amount in dispute and the impact of the COVID-19 pandemic, the local courts ruled to dismiss the lawsuits. In 2024, after the client filed a lawsuit for the third time, the case was, following an application for elevation of jurisdiction, lawfully elevated to the Intermediate People’s Court for first-instance trial.
3
Precisely Targeting Two Key Breakthroughs: Settlement and Appraisal
The legal team argued that the project owner and contractor had bypassed the actual contractor to proceed directly with settlement, and that the settlement contained errors such as omissions and failure to account for additional costs resulting from changes. Consequently, the settlement outcome could not be enforced against the actual contractor, and the project owner remained liable to pay the actual contractor for the outstanding construction costs.
In response to the client’s defense—which cited a judicial interpretation stating that “where an agreement on the settlement of construction project payments has been reached prior to litigation, a request for expert appraisal during the proceedings shall not be granted”—the legal team conducted extensive research on favorable precedents and submitted a case report. Ultimately, the court commissioned an expert appraisal agency to conduct a re-appraisal of the construction process changes, and the expert appraisal opinion served as a key basis for the court’s decision.
4
Meticulous Review by Three Levels of Courts; Supreme People’s Court Ultimately Rules in Favor of the Plaintiff
After deliberation, the court of first instance determined that the client was the actual contractor for the project in question; the Civil Aviation Airport Company and the general contractor had conducted the settlement without the consent of the actual contractor, and the results of that settlement could not be enforced against or bind the client. The court accepted the expert opinion and added the additional costs resulting from the changes to the original settlement.
The Civil Aviation Airport Company, dissatisfied with the ruling, filed an appeal. The Higher People’s Court, in its second-instance judgment, dismissed the appeal and upheld the original judgment.
The Civil Aviation Airport Company then applied to the Supreme People’s Court for a retrial, citing multiple grounds for retrial, including that no construction contract relationship existed between the parties, that it had already settled accounts with the contractor and made full payment, and that the expert opinion constituted illegal evidence.
After review, the Supreme People’s Court held that: the principal’s primary obligation is to pay the full project price; the Civil Aviation Airport Company was fully aware of and acknowledged the circumstances of the project in question as actually constructed; the project had been accepted as qualified and put into use; and it should pay the corresponding consideration for the work performed; Since the actual contractor did not participate in the settlement between the project owner and the contractor, its application for an expert appraisal regarding the portion of the project involving process adjustments—on the grounds that the settlement review report contained errors—does not violate the provisions of Article 29 of the Judicial Interpretation (I) on Construction Projects.
The Supreme People’s Court issued a ruling dismissing the Airport Company’s application for retrial. The judgment in favor of the client was thus finalized.
5
Significance of the Case:
Some Guidance on Protecting Contractors’ Settlement Rights
The judicial principles established and applied in this case hold certain reference value for similar cases:
First, the settlement between the project owner and the contractor cannot be used against a contractor who did not participate in the settlement. The People’s Court may determine the amount of project payment due to the contractor based on the conclusions of a cost appraisal.
Second, the Supreme People’s Court further clarified the scope of application of Article 29 of the Judicial Interpretation (I) on Construction Projects—the rule that “a settlement agreement reached prior to filing a lawsuit precludes an application for appraisal” does not apply to contractors who did not participate in the settlement, thereby providing a reference for contractors to protect their rights through judicial appraisal procedures.
Third, in the absence of established quota standards, inferential appraisal opinions issued by appraisal agencies based on appraisal criteria and objective facts may serve as the basis for a ruling.
From the initial filing of the lawsuit to the Supreme People’s Court’s final ruling, this case spanned more than four years, involving three filings, a transfer to a higher court, two levels of trial, and one retrial review. Amid a complex situation marked by repeated procedural obstacles and intertwined disputes over settlement and expert appraisal, the King&Capital Law Firm team remained steadfast in focusing on the fundamental facts of the case and its core legal basis, ultimately securing a definitive victory for the client through professionalism and perseverance.